Constraints...
In the Open Standard
Andrew MusulinMember for 19 years 3 months
- Created
- 3
- 2
0
I currently have a running schedule with no constraints added in for the project complete milestone...I have since progressed the schedule and the expected completion date has pushed out by 2 months or so. I wish to see the amount of negative float I have, so I added a constraint to the original contract completion date to see the negative float but it does not anchor and it continues to get pushed out to the new revised completion date.
What am I missing?
What am I missing?
3 replies