G’day,

In P3 you can copy and paste codes between activities, which is a great time saving task. In P5 you need to change each activity individually. Is there a way to bulk copy codes between activities ?

Keep Planning,

Kevin.

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Kevin
    In P5 it’s much easier to assign codes than in 3.1.
    On the right side of the screen there are some icons, Number 4 from below is "Assign Activity Codes". Now you can select groups of activities and assign codes to them - or remove codes from them.
    "Fill Down" works very similiar to P3 3.1.
    Regards
    Dieter