Skip to content

V5 : Copying Actvities of one project to other

Amar AghanaMember for 21 years 2 months
Created
13
5
0
How to copy activities of one project to other project?

( I have Activities A01, A02 in Project P001. I want to copy A01 and A02 to Project P002. I tried opening both project and tried to paste. Could not succeed)

13 replies

Oldest first
  1. 0
    Marcio Sampaio ·
    Open both projects. Than copy and paste.
  2. 0
    Shah Shams Alam ·
    Select both the projects in Entrprise breakdown structure using controll key. Right click and open, Both the projects will open. Now u can copy and paste.
  3. 0
    Alex Wong ·
    Amar

    If you copy the activities in one project first, open both and organise it by EPS/WBS. Then you can select them and drop it into the project you wand to paste. Make sure you have rights to both projects.

    HTH

    Alex
  4. 0
    Amar Aghana ·
    Alex,

    I have projects structured by activity codes not by WBS. When I open two projects and try to paste, it could not be done.

    However, by default, WBS Level 1 is project itself. I grouped two projects by WBS for Level 1 and then tried. It worked out!
  5. 0
    Alex Wong ·
    Thats right becasue the software need to know which Node (EPS) you want to paste the activity that why you either group by "EPS/WBS" or Just "WBS"

    Alex
  6. 0
    Amar Aghana ·
    Alex, Thank you.

    Thanks to all for participation.

    Cheers, Amar.
  7. 0
    Muhammad Iqbal ·
    hi
    guys

    why not u using "fragnent"

  8. 0
    Alex Wong ·
    MUHAMMAD

    It is P3e not P3 therefore there is no such thing as fragnet.

    Cheers

    Alex

  9. 0
    Harold Martin ·

    Muhammad,

    Highlight the activities you want to copy go to tools fragnet, store fragnet put ID & title, then open other project go to fragnet, retrieve fragnet than select.

    kind regards,

    Harold
    infrastructure/tower projs.
  10. 0
    Marcio Sampaio ·
    What!!??
  11. 0
    Marcio Sampaio ·
    Dear all;

    This forum is for P3e users. We have another forum for P3 users.

    Using this one to discuss about P3 cause confusion.

    Best regards.

    Marcio Eduardo.
  12. 0
    Wilmore Makonese ·
    I would suggest exporting the project( or activities ) you want and then importing it/them in the project you want it/them to be.
  13. 0
    Henk van der Heide ·
    Open both projects, the one you want to copy from and the one you want to paste to.
    Organize bij WBS, select the activities, copy, and past within the WBS of the new project.
    You can also paste in the same project, now you have the activities double, and change the WBS of the copied activities

    Because P3e is full multiproject you’ve to difine the wbs for each activity. When you dont use WBS it puts all activities in the same project (what’s a part of the WBS)


    regards,

    Henk

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?