P5 Resource Leveling

Trevor LyleMember for 19 years 4 months
Created
0
2
0
I have a labor resource called LAB. I can resource level across open projects and/or by defining Project Leveling Priority.
How can I level across the enterprise for LAB with Area=21 and then Area=30 (I suggest Area would be a user-defined field)?
The LAB resource is similar but is NOT interchangeable from Area to Area. I do not want to go the route of designating each area with it’s own LAB resource (e.g. LAB21, LAB31 etc.) - there would be several thousand possible combinations.

Has anyone come across a similar problem and identified a method or workaround? Primavera could not help and only offered to put it on their "wish list".

Any suggestions would be greatly appreciated.

Replies

Oldest first

No replies yet. Be the first to answer.