Integrating and updating the Project activities

Arslan UsmaniMember for 19 years 4 months
Created
1
5
0
Guys,

i am integrating the activities into P6 and the field based activities are coming and Contractors, can you suggest that how i can update these. as i understand if we have the same WBS, we can then import the activities from them and update the integrated plan. Biggest fear is the update, is this need some more fine tuning. do we have to have the same activity codes nad user define codes etc.
i appreciate.

Cheers, Arslan.

1 reply

Oldest first
  1. 0
    David Kelly ·
    If you have P6, then the solution is to give all the field guys the Web Applications nad make them update their own activities.

    An end to Import, Cut and Paste for ever!