Integrating and updating the Project activities
In the Open Standard
Arslan UsmaniMember for 19 years 4 months
- Created
- 1
- 5
0
Guys,
i am integrating the activities into P6 and the field based activities are coming and Contractors, can you suggest that how i can update these. as i understand if we have the same WBS, we can then import the activities from them and update the integrated plan. Biggest fear is the update, is this need some more fine tuning. do we have to have the same activity codes nad user define codes etc.
i appreciate.
Cheers, Arslan.
i am integrating the activities into P6 and the field based activities are coming and Contractors, can you suggest that how i can update these. as i understand if we have the same WBS, we can then import the activities from them and update the integrated plan. Biggest fear is the update, is this need some more fine tuning. do we have to have the same activity codes nad user define codes etc.
i appreciate.
Cheers, Arslan.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?