Equipment usage hours in Primavera

Nadeem AnsariMember for 19 years 1 month
Created
1
4
0
Is there a way to enter equipment usage hours to show progress in P5/P6 i.e. same way as labor (manhours)can be entered to show progress

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Nadeem,

    Yes you can enter equipment usage hours (same as labor manhour) to show progress. If you defined your equipment as nonlabor units then use the nonlabor units budget, actual and remaining text box for your input.