Material resource leveling?
In the Open Standard
Chris HibberdMember for 20 years 6 months
- Created
- 3
- 4
0
Hi Guys, could do with a bit of advice.
I’m developing a schedule at the moment where the principal constraint is volume of water available.
I have tried to set up the water availability as a material resource, but can’t figure out how to change the volume available within a calendar (such that I can have more availability as time goes on)and then use this to level the schedule.
I’m sure that I’ve missed something very obvious! Can anyone offer any help and put me out of my misery?
Many Thanks
Chris
I’m developing a schedule at the moment where the principal constraint is volume of water available.
I have tried to set up the water availability as a material resource, but can’t figure out how to change the volume available within a calendar (such that I can have more availability as time goes on)and then use this to level the schedule.
I’m sure that I’ve missed something very obvious! Can anyone offer any help and put me out of my misery?
Many Thanks
Chris
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?