Longer activity id?

Ali KandemirMember for 21 years
Created
1
3
0
Hello,

Anybody knows if it is possible more than 10 digits activity id in P4 or P5?

thanks

1 reply

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Ali,
    the limit is 20 digits. But you can reduce it under Admin --> Admin Preferences --> ID-Lenghts.

    Another difference to P3: Activity ID codes no longer exist.

    Regards
    Dieter