Level of Effort Resource budget

Kevin TonMember for 19 years 11 months
Created
1
2
0
Hello everyone,

I assigned budget to level of effort and try to display , but I could not.

Could any one help?

Thanks,

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Kevin,

    Display what???

    If you are referring to Bars on your Gantt Chart, you need to define you bars for actual and remaining bars and use Level Of Effort for the Filter to display them.

    HTH,
    Rodel