Level of effort Progress

Sander GorissenMember for 20 years 1 month
Created
3
1
0
Hi there fellow planners,

I was wondering how the f*ck (sorry ... getting irritated) you could let the progress of a level of effort activity update by progressing underlaying activities.

Many thanks in advance!

Sander

3 replies

Oldest first
  1. 0
    Steven Oliver ·
    Because thats why LOE (or hammocks) are convenient to use.
  2. 0
    Niek Zonneveld ·
    Sander,

    Why don’t you use a WBS Summary for that?

    Cheers,

    Niek.
  3. 0
    Sander Gorissen ·
    Thanks Niek,

    but that doesn’t work as it is not part of a WBS. I’ve already found the problem. I incorrectly linked the LOE.

    thanks again!

    Sander