Costomizing SQL Databasses of Primavera

Siavash GholampourMember for 19 years 1 month
Created
13
3
0
Dear Freinds
Hi
I wana costomizing SQL P3e.Could you help me?

Best Regards
Siavash

13 replies

Oldest first
  1. 0
    K D ·
    Hi .
    Please elaborate your request sothat we can help you.

    Thanks
  2. 0
    Siavash Gholampour ·
    Dear Friend
    Thanks for your reply,
    We prepare some databasses for controling activities, for example on Eng. activities we prepare DCI(Document Control Index) database and I want to link some field of DCI to SQL database of P3e,and SQL database of P3e updating automatically. Please guide me if you could. I wish be health and happy you and your familly.I work on oil & Petrochemical projects in IRAN and I will be happy if you call me by phone or other.
    ----------------------------------
    Cell Phone:+98 912 550 6852
    Home Phone:+98 21 77901043
    E-Mail:S.Gholampour@Namvaran.com
    ----------------------------------
    I am waiting for your reply,

    Best Regards
    S.Gholampour
  3. 0
    James Barnes ·
    Siavash

    I suppose that what you’re intending to do is have the issuance of a document (for example) logged by your DCI then automagically trip the completion of the matching milestone in your schedule.

    Fundamentally, speaking from an SQL standpoint rather than a P3e one (as we’re not using it here yet, still on P3), it should be possible. You need to identify the location in the P3e SQL d-base that holds the relevant info and have an update query trip it. P3e may well include security blocks to prevent you doing that, but admin access should get you past them. What you will need is experience with SQL and a knowlege of how P3e and the dbases you want to interface it with implement it.

    However, I think it would be a bad idea.

    The project schedules that I design, build and update involve usually around 20,000 activities, which I believe to be typical of chemical plant turnarounds (but I can only speak for what I do). We update these schedules daily during execution. As such, we have 500 - 1000 activities to update on a daily basis, a job that I and others work an early shift to comlpete by 9am each morning. You can imagine that we have long dreamed about and experimented with various ideas to automate the update process and allow us all an extra couple of hours in bed.

    Believe me we have tried and it always causes problems. Unless your system is really iron clad you will end up with progress being missed or overstated and, worse still, your system may actually be subverted (read elsewhere about bodies issuing incomplete drawings to "achieve" milestones). Worse than all this will be the feeling in the pit of your stomach when someone points out errors in your milestones at a meeting and you can’t explain why because the updating was automatic and thus unchecked.

    For your system to be iron clad it needs to have been run through several projects, preferably subject to attempts at circumvention.

    For me at least, a "first eye" check on the progress updating is essential, especially as I know that my own coding is not always 100% correct but I know that the output that I present at 9am each day needs to be.

    But, really, it’s up to you.
  4. 0
    Siavash Gholampour ·
    Thank James,
    You have good idea for controling & up to dating, but I find many problems on controling Engineering project, controling doc.s & milestones, you are allright for updating schedule but because DCI database filling by many persons that they have responsible for that job, the controling doc,s is very problem and if this database could be automatically progress from that database we could operating activities better than last. but now, we up to dating all of projects same as you.Especially when we have EPC project with near 120000 activities.
    I hear your ideas.

    Best regartds
    Siavash
  5. 0
    James Barnes ·
    well, fair enough Siavash, it’s very much up to you, as I said.

    Roll your sleeves up and take the hood off the SQL d-base. If you get some IT bods to do it for you (rather than planners who know SQL), be prepared for a solution that makes more sense to a d-base programmer than a planner (just my experience!)

    Another way would be to produce a KPI curve (or curves) from the DCI dbase to show docs completed by discipline (or whever suits your needs) then show each of these curves as an activity. This should be fairly simple with an export to Excel (or generate the curve directly in SQL, if you’re confident to) and generates the "human break" where you get the opportunity to review the figures before commiting them to your schedule.

    120,000 activities is a lot I’m not even sure P3.1 can handle so many (although I know p3e is all new and spanky-like
  6. 0
    Dieter Wambach ·
    Hi Siavash
    The German PAR uses the API (A Programmer’s Interface) for an add-on to report progress. I used it already during a turnaround.
    The Primavera’s API is delivered free of charge and using this, you won’t need to creep into the data model. I think, it’s too dangerous to write into the database using SQL.
    Regards
    Dieter
  7. 0
    Siavash Gholampour ·
    Thanks Dieter,
    I will Check it, but could you write web site that I could API delivered free?or trnsfer that for me?My E-Mail is same as below:
    S.Gholampour@Namvaran.com
    Thank you
    Siavash
  8. 0
    Dieter Wambach ·
    Hi Siavash
    When you buy P3e you’ll get an API-license free of charge - but not automatically. Start P5, then have a look under:
    Help --> About Primavera --> System --> under the headline "license" the last line is Integration API NU(x), CU(0)... If x>0, then you just install the API for up to x users - don’t forget the license entry under Admin--> Users. If x is = 0, then you’ll have to ask your dealer for a new license file which should be free of charge for as many users you have a P5 license - and maybe for the API cd.
    Regards
    Dieter
  9. 0
    K D ·
    Hi.
    If you buy P6 ,you will have API license by default.
    Thanks
  10. 0
    Siavash Gholampour ·
    Thanks K.D and Dieter
    My P3e is 4ver. Could you help me please?
    Best Regards
    Siavash
  11. 0
    Dieter Wambach ·
    Hi Siavash,
    For Ver. 4 it was the same procedure. Does your license include the API?
    Regards
    Dieter
  12. 0
    K D ·
    Hi Siavash,
    There is another easier way which you do not have to request license from Primavera is to use SDK (Software Development Kit). It was on CD1 and it use Project Mangement license.
    If your demand is just take out data from database and handle it in another environment, this is the best choice.
    API is used for manipulate data inside Primavera environment.

    SDK Overview
    The Primavera SDK makes Project Management data available to external applications. In addition to data, the Primavera SDK provides application business rules and calculated values that facilitate integration with customer databases and applications.
    The Primavera SDK makes Primavera data available via an Open Database Connectivity (ODBC) type interface and is also compatible with any ODBC client. ODBC clients include programming languages such as VB, PowerBuilder, C++, scripting tools, and so on. The SDK requires some expertise in extracting data from a database (typically, using Structured Query Language (SQL) queries or programming tools), along with some knowledge of the application schema (tables and fields). The SDK supports both read and write of Primavera data.

    Thanks
  13. 0
    Siavash Gholampour ·
    Dear Friends
    Thanks for your guids, in truely I am interested to ask you what do you if you should controling a plan over than 120000 activities, in Eng. , Procurement and Construction levels.I m waiting for your points.

    Best Regards
    Siavash

Log in or join to reply