S Curve Late Dates
In the Open Standard
Philip RichardsMember for 19 years 1 month
- Created
- 4
- 1
0
Any advise please?
I have produced an S Curve Report in P5, based on subject area ’Activity Resource & Role Assignments’. It shows Early Target (based on ’Remaining Early Cost’, and Late Target (based on ’Remaining Late Cost’.
I now need to incorporate ’cost account’ costs.
The problen is, that when I run the Report Wizard (based on subject area ’Activity’), there is no option under the ’Time Interval’ field, to show ’Remaining Late Cost’. Only Remaining Total Cost is available (whic will be based on Early dates.)
Only way I can think of to get the ’Late Costs’, is to re-schedule the activities to happen as late as possible (Backward Pass), but cannot find a way in P5 to do this.
Can anyone help please?
I have produced an S Curve Report in P5, based on subject area ’Activity Resource & Role Assignments’. It shows Early Target (based on ’Remaining Early Cost’, and Late Target (based on ’Remaining Late Cost’.
I now need to incorporate ’cost account’ costs.
The problen is, that when I run the Report Wizard (based on subject area ’Activity’), there is no option under the ’Time Interval’ field, to show ’Remaining Late Cost’. Only Remaining Total Cost is available (whic will be based on Early dates.)
Only way I can think of to get the ’Late Costs’, is to re-schedule the activities to happen as late as possible (Backward Pass), but cannot find a way in P5 to do this.
Can anyone help please?
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?