Different resource rates seen by different users

Andrew DickMember for 19 years 8 months
Created
7
3
0
I have just discovered something weird and am really hoping that someone has found this before and can sort me out.

There is a difference between rates assigned to a resource when viewed by the administrator and seperate users.
The difference in around $20 an hour.

Why is this happening at all, we are all on the same data base.

If the rates are adjusted by the admin, they are escalated for the user and if set by the user they are deescalated for the admin.

Help please

Andy

7 replies

Oldest first
  1. 0
    K D ·
    Hi Andy.
    This is really weird.
    Each resource have 5 different rate type which was defined while you create resource.
    We are not sure of the error reason but I think you should check some following element which can be different between administrator and user account:
    _ rate type, rate source in Resource tab of Activity detail.
    _ effective date at Unit&Price tab of Resource window.

    Thanks
  2. 0
    Andrew Dick ·
    Thanks for that response, however, the rate type and source are the same for both login profiles, as is the effective dates.
    The user preferences are the same too.

    It’s just that you get 2 very different figures from one user to another.

    ?? Is there anywhere in the system where you can set a currency conversion rate for resource rates, across different users?????

    Long bow, but worth asking as this is how it acts.

    Andy
  3. 0
    K D ·
    HI Andrew.
    We think there is not such option.
    Maybe this is a Primavera bug.
    You’d better check on Primavera’s POINT page.
    Thanks
  4. 0
    Andrew Dick ·
    Have done so, will advise response if I get one
  5. 0
    Andrew Dick ·
    So it turns out the user preference tab for currency had different settings on the two users. One was in Aussie Dollars the other in USD, hence the behavior similar to a currency converter.

    Now I wonder how you set the exchange rates???????

    Andy
  6. 0
    Rodel Marasigan ·
    Andrew,

    You can change the exchange rates under Admin-> Currencies and you can set the currency used per user under Edit-> User preferences-> currency and select a currency for viewing monetary values.

    Hope this help,
    Rodel
  7. 0
    Andrew Dick ·
    Thanks for that

    Appreciate it

    Andy