Updating P5

Sandy MathesonMember for 22 years
Created
3
1
0
Doing something I though was simple, update Physical % complete by import of Excel data file (using format from previous export). Will not work for some reason, tried several times. On import I get message that ’import is successful’, but no data in field. I can type the data in the field but not into long term typing exercise. Have managed to import start dates and RDU etc (after a few tries and losing WBS in process) but not %??? Does anybody else find this import/export feature a real pain in the a$$?? Every step, every time, in some cases will only read 1 field, sometimes more. GGGGGGH.

3 replies

Oldest first
  1. 0
    Tomas Rivera ·
    Sandy:

    I have had the same problem as you have.
    According to Primavera, you need to update the Activity % Complete field in your Excel file. Then when importing, the scheduler will update the corresponding % complete field depending on the % complete type you have configured for each activity.
    But I still get the same problem again sometimes. So I am not sure what is going on.

    Hope it helps

    Tomas Rivera
  2. 0
    Sandy Matheson ·
    Thanks Tomas, that worked. But still a painfull process to update progress, this import/export is tedious. Why can we not update all required fields with one file import!!
    Sandy
  3. 0
    Tomas Rivera ·
    Sandy:

    The only fields I update are start and finish dates and activity percent complete. I do it all 3 in one import session and it works fine except for the ocasional errors in the percent complete as I mentioned before.

    Do you have to do the import of activity percent complete after doing the import of dates for the percent complete to come up right?

    Tomas Rivera