Updating Activity Percentage Complete
In the Open Standard
Anbin PonnithMember for 17 years 4 months
- Created
- 11
- 6
0
Dear All,
I Exported a set of activities to Excel and I changed the percentage complete and then imported back.But it is not getting updated in P6.
Is it not possible to update activity percentage complete in this way.
Please give me a solution,
With Thanks & Regards,
Anbin
I Exported a set of activities to Excel and I changed the percentage complete and then imported back.But it is not getting updated in P6.
Is it not possible to update activity percentage complete in this way.
Please give me a solution,
With Thanks & Regards,
Anbin
11 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?