I would like to put a schedule constraint on the last task of my project; this task being a milestone, I cannot use Expected Finish; when I use Finish On or Before and put a date sooner than the Planned Finish date, PM5 shortens the project duration by the difference between Finish On or Before and Planned Finish.
How can I get PM5 to calculate and display a negative float instead?
Have a good week-end, and thanks all for your help
Alexandre
I would like to put a schedule constraint on the last task of my project; this task being a milestone, I cannot use Expected Finish; when I use Finish On or Before and put a date sooner than the Planned Finish date, PM5 shortens the project duration by the difference between Finish On or Before and Planned Finish.
How can I get PM5 to calculate and display a negative float instead?
Have a good week-end, and thanks all for your help
Alexandre
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?