Methodology Manager - Updating Model

Mark ChapmanMember for 20 years 5 months
Created
2
1
0
I have a model in MM but I cannot add a new activity or modify existing activities.

I think last time I checked in but this is a pain in the a***. What’s the best way of managing this model?

2 replies

Oldest first
  1. 0
    Mark Chapman ·
    Ok that was the wrong question really. I shouldnt have had this checked out and its now checked back in. So I can make modifications again.

    In the past I have had to check the model out in order to use this as a template in PM. I believe I shouldnt need to do this. So what am I doing wrong?
  2. 0
    Karim Mounir ·
    Other idea u can do is to export sch. once used in PM (to be as a template).
    When needed just import the xer.