Skip to content

P5 CANT CHANGE E/S TO ACTUAL DATES

Donovan GovenderMember for 20 years 10 months
Created
2
3
0
Please help urgently, I have imported a MSP project to P5, I have set my schedule and have baselined the schedule and now when I want to progress and put in actual dates it won’t change to new actual start dates

2 replies

Oldest first
  1. 0
    Rony Roberto ·
    Don,
    go to status, click the actual date,then put a value on the peercent complete.




    Regards,
    rony
  2. 0
    Donovan Govender ·
    Thanks Rony

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?