P5 Why does my baseline bar move when i update

Donovan GovenderMember for 20 years 10 months
Created
6
3
0
P5 Why does my baseline bar move when i update logic
things like this always happens when you are in a rush

Please help

Regards

Donovan

6 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Donovan,

    Are you using Assigned Baseline or a current project as a baseline?

    HTH,
    Rodel
  2. 0
    Donovan Govender ·
    Hi Rodel,
    When I created the baseline, i chose project, maintain baseline,selected the current project i was in,clicked add.

    now when I open maintain diologue box it shows the project name and baseline name,
    under basline name- it shows the baseline
    in baseline type - it shows "none"
    data date -24 sep 07
    in last update date- it shows 9 Oct 07
    now I dont if 9 oct07 should be there,maybe i did something to cause it to go to 9 oct 07 i have updated my schedule on 5 oct 07, and now on 12 oct07.
    what have done wrong or did I not do

    Regards
    Donovan

  3. 0
    Rodel Marasigan ·
    Donovan,

    If you chose a current project as a baseline then your baseline bars will move when you change the logic. You have to save your current project as new file and assigned that as a primary baseline. Any changes to your current project will not affect your primary baseline.

    To save current project as baseline:
    1)     Select Project -> Maintain baseline
    2)     Click Add and Tick “Save a copy of current project as a new Baseline” and click Ok
    3)     Select Project -> Assign baseline
    4)     On User Baseline under Primary -> Select the new save baseline from the dropdown box and not the current Project.
    You should have a fixed primary baseline.

    Hope this help,
    Rodel
  4. 0
    Donovan Govender ·
    Thanks guys, I did not have my baseline in the primary box- it was still current


    Regards

    Donovan
  5. 0
    K D ·
    Hi.
    And be sure that you show the correct bar in Gantt chart.
    Sometime we assign baseline to project-baseline but show out Primary-baseline in Gantt chart.

    Thanks
  6. 0
    Nikhil Menkudale ·
    Hi, this is Nikhil.
    You have made a user baseline. You must have selected current project as project baseline in Assign Baseline dialouge box.
    You should go to Bars in gantt chart . There you mark the check-box of primary baseline bar & in timescale column next to bar column you select primary baseline.

    Hope this should help.

    If not, pls send me screenshots of how you are maintaining & assigning baselines to my mailid.
    nmenkudale@gmail.com

    Regards
    Nikhil