Resource Loading in P5
In the Open Standard
Beth SpiveyMember for 19 years 9 months
- Created
- 7
- 2
0
In the course of building an EPC schedule in P5 I cannot get the resource to load and calculate the units properly. I have set the duration to "Fixed Duration & Time/Units". I enter my resource and then enter the budgeted units but it will not calculate the budgeted units/time. My theory or the way P3 worked is units X duration X calendar = manhours. I also want to reflect acutual man units in order to run histogram and manually level my schedule. Also, if you have (example) 5 carpenters, do you enter that resource 5 times or enter once and change the budgeted units to 5? I changed the Time Units per Hours under Admin Preferences to reflect 10/d 50/w 200/mo 2400/yr. HELP! What am I doing wrong?
Thanks
Thanks
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?