Critical Path though Multiple Projects
In the Open Standard
David KellyMember for 21 years 11 months
- Created
- 5
- 3
0
After all these years I have a question for you all rather than just answers!
P5/P6 encourage the use of multiple projects to model one "real world" project - but what if we want just one critical path?
Primavera’s work around (and I don’t need all you old P3 hands to tell me "use P3") is to use the multiple float paths calculation, group and sort the project by this, and kinda hope the first/second path is the real critical one?!
What is wrong with setting all the member projects to the same must-finish-by date?
P5/P6 encourage the use of multiple projects to model one "real world" project - but what if we want just one critical path?
Primavera’s work around (and I don’t need all you old P3 hands to tell me "use P3") is to use the multiple float paths calculation, group and sort the project by this, and kinda hope the first/second path is the real critical one?!
What is wrong with setting all the member projects to the same must-finish-by date?
5 replies
Oldest firstLog in or join to reply