Skip to content

new project problem "negative float" (p3e)

Richard BowieMember for 20 years
Created
3
3
0
I took a copy of an old project and changed all the constraints, changed the project start date and the data date. the new project has no visible relationships to other projects. when i go to schedule the project i get a popup infoming me that not all open projects have the same data date, but they do. the only thing i can see is that the late start is still the same as the original project where the start date and early start dates are correct to the new project.

3 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi
    This message - not all .. - is quite reliable: one minute of difference is a difference. For control, change your preferences to "show time".
    Edit --> User preferences --> Dates
    Then you’ll realize the difference.
    For the other item, go into the view "Projects" --> Tab Dates and check "Must finish by". I assume you forgot one project.
    Regards
    Dieter
  2. 0
    James Skelton ·
    If the old project had cross project (external links) then when you schedule in V5 it hold these links by using External early start or External late finish dates.

    If you have cleared all your known constraints but still have the * in the date field then this might be your problem.

    Run a filter for External early start or External late finish and clear any External dates then schedule your project.

    Hope this helps
  3. 0
    Richard Bowie ·
    Spot on Mr Skelton i knew an Ex Babcock guy would come to the rescue.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?