new project problem "negative float" (p3e)
In the Open Standard
Richard BowieMember for 20 years
- Created
- 3
- 3
0
I took a copy of an old project and changed all the constraints, changed the project start date and the data date. the new project has no visible relationships to other projects. when i go to schedule the project i get a popup infoming me that not all open projects have the same data date, but they do. the only thing i can see is that the late start is still the same as the original project where the start date and early start dates are correct to the new project.