Hello,
I have been using P5 since last couple of months coz I shifted from P3 to P5.
I am facing a problem with built in graphical loading reports in P5. The tabular reports are excellent but where are the graphical ones?

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Mohammad,

    P5 don’t have graphical reports save like P3. It’s WYSWYG option (what you see what you get). Means what ever you have on your screen is your graphical report. You can have different layouts saves under view->layout on P5 menu.

    Hope this help
  2. 0
    Alex Wong ·
    Yep

    From P3e 3.5 to now P6, graphic report is one of the weakness that everyone is complaint. But if you are using the P6 web access then some good graphical report can be produce though the portfolio layout.

    Al
  3. 0
    Edderic See ·
    Hi,

    Besides graphical reports generated in P3 has its own flaw: not presentable.

    Regards,

    Ed