Dear All,

In order to create a progress report I am using the STEPS feature of P3e to export the products that I wish my contractor or internal supplier to provide updates on periodically.

I’ve used the custom text fields (in the steps tab) to create some appropriate fields which i then export into excel and will send on this report in order to get the contractor/internal supplier to update it.

I would then like to re-import this data (i.e. the updated completion date of the product) from excel into the relevant field in P3e.

I can create the report and export from P3e into Excel easily enough but how do I import excel data into the custom STEP fields in P3e? Is it possible?

Thanks,

Murray

4 replies

Oldest first
  1. 0
    K D ·
    Hi Murray
    Primavera POINT have a excel tool which can export activity step. You can try it in your problem.
    Regards
  2. 0
    Mark Chapman ·
    Hi Muzza,

    I have a macro taken from POINT but this only works if you have SDK - fiji.

    Best regards,

    Mark
  3. 0
    Murray Allen ·
    SDK? the joys of acronyms.

    I took a look at POINT and the spreadsheet tool is shown as unsupported for P5?

    Fiji? hmm, how about Russia, the boks and Raikonnen?

    MOSCOW

    Muz
  4. 0
    K D ·
    Hi,
    You can have a look at prim4617