Any idea what I am doing wrong? I don’t have a baseline bar for the new activity updated to the baseline. I have tried the workaround as suggested from POINT but still no baseline bar.Oh and I’m on sp4.
Solution ID: prim27158
When Updating a baseline for Added activities the baseline data for the new activities does not display.
Status: Reviewed
Version(s): 5.0
Problem: When Updating a baseline for Added activities the baseline data for the new activities does not display.
Problem: Baseline bar does not appear for new activities added to the baseline.
Fix: This known problem in Project Management has been corrected in version 5.0 Service Pack 3.
Fix: Workarounds:
Go to Project, Assign Baselines and then click OK
Close and reopen the project.
Solution ID: prim27158
When Updating a baseline for Added activities the baseline data for the new activities does not display.
Status: Reviewed
Version(s): 5.0
Problem: When Updating a baseline for Added activities the baseline data for the new activities does not display.
Problem: Baseline bar does not appear for new activities added to the baseline.
Fix: This known problem in Project Management has been corrected in version 5.0 Service Pack 3.
Fix: Workarounds:
Go to Project, Assign Baselines and then click OK
Close and reopen the project.
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?