I am progressing a schedule in P6. Activity Bars that have started before their baseline early start now have a gap between the data date line and the start of the remaining work bar. Is there a way to default the remaing work bar to start at the timeline? I have tried some of the scheduling options but none fix the problem for all the affected tasks. Any help appreciated.