why does budget hrs change when increasing remaining

Donovan GovenderMember for 20 years 10 months
Created
2
2
0
why does budget hrs change when increasing remaining
and activity has not started

2 replies

Oldest first
  1. 0
    David Kelly ·
    Because your "duration type" has units per time unit fixed.
  2. 0
    Rodel Marasigan ·
    Donovan,

    Mark is correct. Check the settings under Project Screen-> Calculation Tab and un-tick the "Link Budget and At Completion for not started activities". This should answer your query.

    HTH,
    Rodel