Dealing with Variations to activitiy scope
In the Open Standard
Neil BradyMember for 19 years 9 months
- Created
- 0
- 2
0
Guys
Could really use your help on understanding how the industry deals with variation to an activity scope
For example if I have an activity with 100 manhours in it with a duration of 6 weeks - If I get a variation at week 2 for 30 man hours and 2 more weeks duration .......
I could add this directly to the activity - but this gives no real ability to track or report
I could creat a new activity - enhances reporting but could get messy if you are time writing at activity level (imagine if you have 50 variations)
How do you guys dealt with and track this in industry ?
Let me know
Neil
Could really use your help on understanding how the industry deals with variation to an activity scope
For example if I have an activity with 100 manhours in it with a duration of 6 weeks - If I get a variation at week 2 for 30 man hours and 2 more weeks duration .......
I could add this directly to the activity - but this gives no real ability to track or report
I could creat a new activity - enhances reporting but could get messy if you are time writing at activity level (imagine if you have 50 variations)
How do you guys dealt with and track this in industry ?
Let me know
Neil
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?