Activitiy details

Raji Umapathy RajiumapathyMember for 20 years 3 months
Created
1
1
0
I have experiance in construction planning
so far i have not developed EPC project schedule

in this connection what are the activities will come under detail engineering site ( in oil & gas industry project )

inthis regard can you help

1 reply

Oldest first
  1. 0
    Randy Taylor ·
    Regarding (EPC) Engineering, Procurement, Costruction.
    Depending on the field, if you were only working to define the Engineering aspect. You would tipically use detail from the engineering department to develop your WBS. Example:
    Project Management
    Pipeline
    Facilities
    Hydraulics
    Electrical
    Survey
    ROW
    Each department should be able to provide you with details that will help you establish the activities, manhours, expenses needed that will fall under these categories.
    Hope this helps you get started.