Resource availability

Dattatreya PadharthiMember for 23 years 6 months
Created
5
2
0
Friends,

How do u display resource curves at a higher level.

I have 3 piping engrs having different holiday cycles; Their holidays have been fed in P6, I am unable to get combined piping availability.
Am I missing something here?

Cheers

Datta

5 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Dattatreya,

    Quick work around is to highlight all resources shown on Current Project Resources window on the bottom left of the screen or right click the said window and select Group & Sort by-> Customise. Tick Show Grand Totals then click Ok. Select Total and that should combine all your resources.

    HTH,
    Rodel
  2. 0
    Dattatreya Padharthi ·
    Hi Rodel,

    Thanks a lot; but I forgot to define hierarchical resources properly.

    Cheers

    Datta
  3. 0
    Dattatreya Padharthi ·
    Hi Rodel,

    In P3, We define normal & hierarchical resources
    we define resource availability (normal/max) thru dates.
    But we also get hierarchical resource availability in P3 on the basis of normal resources.
    How do we get hierarchical resource availability in P6.

    Any thoughts ?

    Cheers
    Dattatreya
  4. 0
    Rodel Marasigan ·
    Hi Dattatreya,

    It almost the same as P3 with enhance and added function. In P5/P6 you can define Resource Breakdown Structure (RBS). Assign Roles and Timesheets.

    You set resource availability under Unit & Prices Tab.
    You can set default Unit/Time, Auto compute actuals and select labor, nonlabor and material under Detail tab.
    You can define Driving Resources under Enterprise-> Project-> Resources Tab.

    Hope this help,
    Rodel
  5. 0
    Dattatreya Padharthi ·
    Rodel,
    Thanks; all have been defined.
    For individual resources its fine;
    If u have 3 process engrs(PR1,PR2,PR3) at hierarchical level define addnl res as PR*.
    Define respective(PR1~3)availabilities & you get PR* availability automatically.
    I am still to get these in P6.

    Cheers

    Datta


Log in or join to reply