Skip to content

Display progress on target bar for P5

Jerry LanMember for 20 years 1 month
Created
1
2
0
Dear all,

In P3, there is the option whereby we can display progress on target bar. I do not want to display progress on the current bar. I think that was very good thing in P3. Is this possible in P5? If yes, how? Thanks in advance!


Regards,
Jerry

1 reply

Oldest first
  1. 0
    Andrew Pearce ·
    I put up a similar posting earlier this year.
    It is possible to overlay a %complete bar on a baseline bar, the problem is that the % bar is drawn starting on Actual start date, not on baseline start date as in P3.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?