Incorrect Durations Showing
In the Open Standard
Matthew LovkisMember for 19 years 10 months
- Created
- 4
- 4
0
Hi Folks,
I have created a simple schedule which lasts for exactly 24 months. The original duration was a little longer because I had used the wrong calendar. I changed the dates to the correct duration AND now my At Complete Duration and Remaining Duration says 29 months instead of what is clearly 24 months.
This is highly annoying as I want to use MONTHS as the time increment.
Why does Primavera show the project as lasting 29 months when it is actually exactly 24 months long.
Thanks a lot,
Matt
I have created a simple schedule which lasts for exactly 24 months. The original duration was a little longer because I had used the wrong calendar. I changed the dates to the correct duration AND now my At Complete Duration and Remaining Duration says 29 months instead of what is clearly 24 months.
This is highly annoying as I want to use MONTHS as the time increment.
Why does Primavera show the project as lasting 29 months when it is actually exactly 24 months long.
Thanks a lot,
Matt
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?