Incorrect Durations Showing

Matthew LovkisMember for 19 years 10 months
Created
4
4
0
Hi Folks,

I have created a simple schedule which lasts for exactly 24 months. The original duration was a little longer because I had used the wrong calendar. I changed the dates to the correct duration AND now my At Complete Duration and Remaining Duration says 29 months instead of what is clearly 24 months.

This is highly annoying as I want to use MONTHS as the time increment.

Why does Primavera show the project as lasting 29 months when it is actually exactly 24 months long.

Thanks a lot,

Matt

4 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Hi Matt,

    Check your Hours per Time Period setting. Make sure it match to your calendar settings. Durations are calculated from the Hours per Time Period which can be set on Admin preference or User preference under Time Units Tab if “Allow users to specify the number of hours for each time period” is tick.

    Hope this help,
    Rodel

  2. 0
    Taher Abdel-Aziz ·
    Hi Matt,
    Be sure that the default calender is the same project calender. Primavera use the default calender in rolling up the duration information regard less the project calender.
    Hope this help,
    Taher
  3. 0
    Patricia Le Clainche ·
    Hello,

    I agree with Taher.
    We already spoke earlier about this topic. Please refer to http://www.planningplanet.com/forum/forum_post.asp?fid=&Cat=8&Top=33537

    Kindest regards.
    Patricia
  4. 0
    Matthew Lovkis ·
    Thanks a lot folks.

    It was that simple. The default calendar was incorrect for the schedule.

    Cheers,

    Matt