Copy WBS structure to Activity code

K DMember for 19 years
Created
3
5
0
Hi all,
Our company need to apply a new WBS structure, but we want to get back the old structure in some case. So we create a activity code system which identical to WBS structure. In future if we want to get back, simple group to Activity code.
But our WBS structure is really huge. Can anyone give an idea how to copy WBS structure to Activity code fastly? Currently I’m doing copy manually. Very slow.

Regards

3 replies

Oldest first
  1. 0
    David Kelly ·
    You can use p3 3.1 as an intermediary. Export to P3 3.1, then when you import you can select to import the WBS as an activity code
  2. 0
    K D ·
    Hi david
    Thanks for your solution.
    I’m gonna try it. It sound very cool.
    Thanks
  3. 0
    Hemanth Kumar ·
    Great Idea
    Thanks mate