Total Float P3e

Graeme CaldowMember for 23 years 3 months
Created
6
2
0
I hope someone can help…I have activities start, finish milestones and tasks within my schedule that are 100% complete but still show large amounts of total float. Has anyone else experienced this problem? I want the activities to show 0 Float.

6 replies

Oldest first
  1. 0
    Paul Harris ·
    When I make activities as complete my system displays nul total float, that is there is no value displayed in the total float field.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  2. 0
    Rodel Marasigan ·
    Graeme,

    Check your Project Settings Date. It happens only when Must Finish By date is higher than Finish Date.

    To check: Select Enterprise-> Project then select your Project to check and click Date tab. If "Must Finish By" date is higher than "Finish" Date then remove the "Must Finish By" date.

    Hope this help.

    Rodel
  3. 0
    Ronald Winter ·
    Graeme,

    This condition was introduced two years ago with the release of P5. It was ’fixed’ in the first P5 service patch. (By the way, completed activities really do have float but you really need to understand complex CPM theory in order to understand why.)
  4. 0
    Graeme Caldow ·
    Thanks everyone for the responses.

    Paul, With regard to the system showing null total float, that’s exactly what I want to show. Unfortunately my system does not show this. I don’t know why...

    Rodel, I had checked my Project Settings date previously, I had not entered a date in the must finish by date tab.

    Ronald, I think this P5 Service patch will help.

    Once again everyone thanks for your help.

    Graeme
  5. 0
    Waseem Saber ·
    Graeme,

    check there must be some constraints assigned to some of your milestone activities, there is a possibility one of those activity is constrained and actually finished late, thus causing this float issue, hope this is the scenario and it works, otherwise, let us know, if you found the solution, this is a intresting situation worth consideration.

    cheers

    Waseem Saber
  6. 0
    Wasantha Nanayakkara ·
    Graeme,

    Before you schedule the programme, go to options and
    Select ’’retain Logic ’’ or ’’Progress Override’’ to see how it changes.

    I think it works.

    Wasantha

Log in or join to reply