Skip to content

P3e - Resource

Khairul Izani OthmanMember for 18 years 11 months
Created
1
1
0
hello...

i got problem here..
How 2 assign differance resource in one task..ex: 1 engineer..5 fitter..10 helper..should i use budgeted unit or actual unit or any others?

1 reply

Oldest first
  1. 0
    Patricia Le Clainche ·
    If I understand your problem correctly :
    On Activity View, show the Bottom Layout, and on "Resource tab", add your resources Ids, and then, you just have to fill the Remaining Units ( = Remaining Labor Units) for each of them.

    Best regards.



Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?