P3e - Resource

Khairul Izani OthmanMember for 19 years
Created
1
15
0
hello...

i got problem here..
How 2 assign differance resource in one task..ex: 1 engineer..5 fitter..10 helper..should i use budgeted unit or actual unit or any others?

1 reply

Oldest first
  1. 0
    Patricia Le Clainche ·
    If I understand your problem correctly :
    On Activity View, show the Bottom Layout, and on "Resource tab", add your resources Ids, and then, you just have to fill the Remaining Units ( = Remaining Labor Units) for each of them.

    Best regards.