I have a situation in P6 related to resource requirement/availability.
Till recently we have been using P3 for our stage of project where resources are in short supply and deliverable dates/Work Pack completion are resources dependent who operate on a 7/3 week cycle.
I have been defining engr/designer availability with holiday cycles. Activities are resourced hierarchically i.e engr1 and engr2 as resource availabilities and engr* as resource assignment in the activity.
I was looking at the same kind of solution in P6 either with resources or with roles!
Unfortunately P6 does not retain the concept of resource hierarchy.
Has anyone encountered this before & defining roles is the best answer to this.
Regards
Dattatreya

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?