Remove actuals in P6 (HELP)

Ladi SodipoMember for 18 years 11 months
Created
7
6
0
i need to change the status of an activity from started to not started, but everytime i try to remove the checkmark i get an error ’Cannot set status to Not Started if activity has actuals.’ i need to remove the actuals but don’t know how, someone pls help, i have to turn my schedule out b/4 weeksend.

7 replies

Oldest first
  1. 0
    Scott Hastie ·
    highlight the activity you want to change, go to the status tab, uncheck the finish date, change the physical % complete back to zero, reset the actual & remaining labor units (budgeted quantity)in the labour units box, then you should be able to uncheck the start date, it will ask you Are you sure that you want to change the activity to be Not Started? Jusk click yes and it should work

    Hope this helps,

    Scott
  2. 0
    Ladi Sodipo ·
    Thanks Scott, yeah it worked.PP rocks!
  3. 0
    Zoltan Palffy ·

    here is a link to the

    here is a link to the detailed instructions on how to do this 

    http://pmsite.com/forums/viewthread/3064/

  4. 0
    Khuong Do ·

    Hi,I write an article

    Hi,

    I write an article regarding How to remove actual / progress from Primavera P6 schedule.

    If you're interested, kindly read it here https://doduykhuong.wordpress.com/2016/08/01/how-to-remove-actual-progress-from-primavera-p6-schedule/

    Cheer

  5. 0
    Mohammed Azharuddin ·

    Hi,Quick and easy way to

    Hi,

    Quick and easy way to remove actuals using only 1 Global Change.

    Check out my articel here

    https://www.linkedin.com/pulse/quick-way-remove-actuals-from-p6-schedule-one-go-using-azharuddin/?trackingId=kLitu4dDuCP3jndDcGzifQ%3D%3D

  6. 0
    Zoltan Palffy ·

    How to de-status a schedule1.

    How to de-status a schedule

    1. Choose Enterprise, Projects and select the Calculations tab. Choose to "Link Budget and At Completion for not started activities" and "Reset Remaining Duration and Units toOriginal

    2. Choose View, Columns and add the columns for Actual Labor Units, Actual NonlaborUnits.

    3. Choose Tools, Schedule and set the data date equal to the Project Start Date and schedule.To find the Project Start date, choose Enterprise, Projects. Click on the Dates tab and note the Planned Start date.

    4. For the first activity in the list, set the Actual Labor Units to 0. Highlight the activities inthis column and choose Edit, Fill Down.

    5. For the first activity in the list, set the Actual Nonlabor Units to 0. Highlight the activitiesin this column and choose Edit, Fill Down.

    6. Choose Tools, Global Change and run the 1st Global Change. This will set the Actual Material Units to zero.

    7. Run the 2nd global change which sets the activity status to Not Started. 1st Global Change:

    Subject Area:  Activity Resource Assignments If: Where Resource Type equals Material

    Then:  Actual Material Units  = 0 

    2nd Global change

    Subject Area: Activities If: Where Activity Status  is not equal to  Not Started

    Then:  Activity Status  Equals  Not Started

  7. 0
    Bradley Gibbs ·

    Change Actual Labor Units and

    Change Actual Labor Units and Actual Nonlabor Units to zero.

    You can do this with a global change, by adding columns, or in the status tab switching between Labor Units and Nonlabor using the drop down arrow:

Log in or join to reply