Must finish by

Naveen SubbaiahMember for 21 years 9 months
Created
2
2
0
hi,

I am working on P3e 4.1 & my query is - "Is it possible to have a Must start on & Must finish dates for a project" The logic is I have unlimited supply of resources so I need to fix the start & finsh dates. Also is it possible to have "Must start on & Must finish by" dates for individual WBS elements within a project.

Thanks in advance.
Naveen

2 replies

Oldest first
  1. 0
    Shareef Abdul Azeez ·
    Hi

    Its been quite a while, But what I think is u would have to start your project sectors or WBS structures with a Start mile stone. That would we sufficient. Then after you pull in your programme to the required Must Finish date that is, with out giving any constraints!!!.....,,,,, then finally put the Must finish on date which in P3.0 is in the Project over view and in P5 it comes in the start itself.

    The sole purpose, I think of this must finish date is to get the float in your programme from this particular date else, the programme calculates dates from the Early start which normally during the updation stages of a programme goes out of the Must Finish Date.

    Hope I am right. :)
  2. 0
    Karim Mounir ·
    Hi Naveen,

    You can have a "Planned Start" date and a "Must Finish By" date when you create a new project.
    The "Must Finish By" will lead to have a negative TF if the activities passed this date.

    You can’t have constraints for the WBS Summary activity type but since that the WBS summary is a roll up of activities under it, then you can assign the constraints dates for these activities.

    Regards,
    Karim

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?