Critical Path
In the Open Standard
Jiayin YaoMember for 19 years 6 months
- Created
- 3
- 1
0
Hi,
In P5, the critical path was defined as the total float less than or equal to 0.
When filter the critical path, P5 does not pick up all the activities which total float equals 0.
But when I define critical path as total float equals or less than 1. P5 pick up all the activities with 0 float. I think it is something to do with the hours and times. Can anyone tell me how the P5 works?
And also can anyone please explain the longest path, when should I use it?
Thank you very much.
In P5, the critical path was defined as the total float less than or equal to 0.
When filter the critical path, P5 does not pick up all the activities which total float equals 0.
But when I define critical path as total float equals or less than 1. P5 pick up all the activities with 0 float. I think it is something to do with the hours and times. Can anyone tell me how the P5 works?
And also can anyone please explain the longest path, when should I use it?
Thank you very much.
3 replies
Oldest firstLog in or join to reply