Critical Path

Jiayin YaoMember for 19 years 6 months
Created
3
1
0
Hi,

In P5, the critical path was defined as the total float less than or equal to 0.

When filter the critical path, P5 does not pick up all the activities which total float equals 0.
But when I define critical path as total float equals or less than 1. P5 pick up all the activities with 0 float. I think it is something to do with the hours and times. Can anyone tell me how the P5 works?

And also can anyone please explain the longest path, when should I use it?

Thank you very much.

3 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Jiayin
    The reason is a very simple one:
    Primavera does calculate with decimals. If you’ll change your preferences that decimals will be displayed, you’ll realize that those activities you are missing have a float of 0. which is greater than zero.
    Edit --> User Preferences --> Time units --> ’Show decimals
    Regards
    Dieter
  2. 0
    Ronald Winter ·
    Longest Path is a process, similar to but different from CPM and total float. Longest path is a better measurement of the critical path than using total float, as tracking total float ‘fails’ in instances where multiple activity calendars, LOE, interruptible activities, resource leveling, constraints, and out-of-sequence activities are used. I have an article published on the web about this and enhancements to longest path at http://ronwinterconsulting.com/published.htm. Good luck!
  3. 0
    Jiayin Yao ·
    Hi Ronal and Dieter,

    I got it . That is great .

    Thank you very much .

    Reagrds

    Jia yin

Log in or join to reply