Budgeted resorses moves with data dates

Reza HasheminiaMember for 18 years 10 months
Created
1
2
0
Dear friends,
I’ve faced a serious problem during updating my project schedule, i’ve assigned nonlabour resoreces to activities and set the schedule as initial plan, after update i found the budgeted resorces moved behind the new data date, so that it’s not posible to compare budgeted and actual resources.
please advise.
Many thanks.

1 reply

Oldest first
  1. 0
    Gordon Blair ·
    Have you updated the Resource % complete in the Resources Tab?