Skip to content

Multi suspend activities

Reza HasheminiaMember for 18 years 10 months
Created
1
3
0
Dear friends,
In the cases you have many suspention on an activity, is there any particular way to apply?
Thanks.

1 reply

Oldest first
  1. 0
    Dieter Wambach ·
    Reza,
    In P5/P6 just one suspension is possible. You’ll have to create additional activities.
    Cheers
    Dieter

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?