Setting Work Days?

Ken BarrettMember for 19 years 5 months
Created
7
4
0
Hello all!

I am scheduling a shutdown using P3e but for some reason I can not get it to schedule any resource hours on saturdays or sundays. I have changed the project calendar to 7 day work week and have changed the resource calendars to the same, but still no work scheduled on the weekends. Is there some sort of default I am missing that only allows a 5 day schedule? Any help/advice would be greatly appriciated.

Thanks in advance

Ken Barrett
Jr Planner

7 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Ken
    The project calendar is just a default for new activities.
    I assume you want to plan with fixed durations. So:
    - Activity type: Task dpendent
    - Task calendar: the one with working time during weekend.

    Regards
    Dieter
  2. 0
    Ken Barrett ·
    Thank you for help,

    I have my activity type as Task Dependent, and my calendar is set to 7 day work week, still no time scheduled for weeeknds... any other possible fixes?
  3. 0
    Dieter Wambach ·
    Did you check if the seven day work week calendar really was created as named?
    I don’t know of such a restriction. In neneral we have this situation: 5 work days in Europe (Engineering), 6 with Friday off (Construction) and 7 for lead times.... It works.
    Dieter
  4. 0
    Ken Barrett ·
    I figured out that my activity calendar was wrong. I had my project calendar set to 7 days, resource calendar set to 7 days but my activity calendar was set to 5 days...

    I appricate all your help. This site is an absolute god send for me. I am a 26 year old engineer with little field experience and even less planning experience, but trying to produce scheduling/planning/budgeting/everything else... just flying by the seat of my pants...hahahah... as they say, sink or swim!!
  5. 0
    Dieter Wambach ·
    Good luck!
  6. 0
    Wai Chan ·
    I would also recommend on your display column pick the calender display option, and you can change your calender on your activity. I find that much easier because the schedule i am dealing with involves levee and river work with 6 different calenders, and trust me, the Corps of Engineers has many restriction and simply tie your hands all the time.
  7. 0
    Ken Barrett ·
    That is exactly how i figured it out... and it is for sure the way to go

    Thanks!!!!

    Keep the advice coming!!!

    Ken Barrett

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?