Total Float

Jiayin YaoMember for 19 years 7 months
Created
1
9
0
Hi Guys ,

I put the logics in the Schedule . But under the Total Float columns , some of the activities show the number of the float , but some of the activities did not show anything at all . Can anyone please tell me what is the problem ?

Thank you and Merry Christmas .

Jia yin

1 reply

Oldest first
  1. 0
    Jiayin Yao ·
    Sorry , just find out these activities 100% finish

Log in or join to reply