Exporting Long time-phased data to Excel
In the Open Standard
Jubin AhdiMember for 24 years 5 months
- Created
- 3
- 3
0
Hi All,
I’m facing a problem here. I use P3e V5.0 to control a 3-4 yrs project.
I used to prepare my S-Curves before in excell by exporting the Budgeted Labour Units to excel in monthly time buckets. it would export data with 4*12=48 columns totally.
Now I have to prepare my s-curves from 10th of each month (10th Jan to 9th Feb / 10th Feb to 9th Mar / etc...)
For that reason, I tried to export all the time phased data (Budgeted Labour Units) on a daily basis... then I was planning to summerize the data from 10th of each month up to 9th of the next month.
But again I failed... I am able to prepare such a report and save it either as HTML or TXT. But Excel can not get it throughly....
I think maybe it’s becuase that would require excel to have 48*30 columns (1440 columns) which it seems that Excel can not deliver.
Please advise how can I export big chunks of data to excel without any issue.
I’m facing a problem here. I use P3e V5.0 to control a 3-4 yrs project.
I used to prepare my S-Curves before in excell by exporting the Budgeted Labour Units to excel in monthly time buckets. it would export data with 4*12=48 columns totally.
Now I have to prepare my s-curves from 10th of each month (10th Jan to 9th Feb / 10th Feb to 9th Mar / etc...)
For that reason, I tried to export all the time phased data (Budgeted Labour Units) on a daily basis... then I was planning to summerize the data from 10th of each month up to 9th of the next month.
But again I failed... I am able to prepare such a report and save it either as HTML or TXT. But Excel can not get it throughly....
I think maybe it’s becuase that would require excel to have 48*30 columns (1440 columns) which it seems that Excel can not deliver.
Please advise how can I export big chunks of data to excel without any issue.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?