Hiding WBS When Printing

Ken BarrettMember for 19 years 5 months
Created
3
3
0
I am working on planning a shutdown for a petrochemical company. My WBS structure is laid out using equipment ID numbers. When I print out only a certian piece of equipment my wbs is all printed. is there any way that the WBS can be hidden or masked when printing?

3 replies

Oldest first
  1. 0
    Johny Kesserwany ·
    Try to add "Where Node Type is not equal to WBS" to your filter!

    NB:the filter will not exclude the top level WBS in the report....


    good luck
    JK

  2. 0
    James Shimmon ·
    In the group and sort menu tick the ’hide if empty’ box
  3. 0
    Ken Barrett ·
    awesome!!!! thanks a lot guys!

    Ken