Importing Resources from Excel

Ken BarrettMember for 19 years 5 months
Created
3
2
0
Im am attempting to import an excel spreadsheet, unfortuantly when i get to the resources it all imports correctly except the budgeted units / time. it always comes over as 1. anyone have any idea how to remedy this?

3 replies

Oldest first
  1. 0
    Colin Adam ·
    Ken,
    Sounds like you’re importing on the wrong worksheet e.g resources as opposed to the resource assigments sheet (TASKRSRC) The columns you need are task_id , rsrc_id , target_qty and worksheet name should be TASKRSRC. Where target_qty is the number of manhours for the identified resource.
    Also make sure you delete the row that has ’delete row’ at the end of it. Sounds dumb but some people say they don’t do it and it works fine. My experience is that if you don’t and you’re importing hundreds of resource assignments then you get and error.
    Do this daily and it works fine.

  2. 0
    Ken Barrett ·
    Thanks Colin,

    After a lot of experimentation I finally figured out a way that works. Im sure that there are several ways to acomplish this taks. But it seems that to get the correct budgeted units / time (especially on supporting resources) it is nessicary to import the taskrsrc worksheet twice. sounds kind of goofy but had no problems with it.

    Thanks again for your response!
  3. 0
    Colin Adam ·
    Ken,
    Have only heard of importing twice due to a constraint date bug in P5. I have to do this, so no it doesn’t sound goofy!!