activity date not changing
In the Open Standard
Shahzad AhmadMember for 18 years 8 months
- Created
- 3
- 2
0
Hi all
In P6 schedule an activity having 5 activity as a predecessor one of in all ready in progress and one is Constraints which is fouandation ready for Instal...
predecessor Constraints activity starting
date is 29 Jun 09* ( Activity DC00100)
successor of above actvity is Installation of equipment.
(activity EQ001010)
which will be start on 29 jun-09
I have links ss with Activity DC00100 with 0 lag as (predec)after schedule f9
i am wondering activity EQ001010 start date is 20 april 09
can any one advise why it is so...
Thanks
shahzad
In P6 schedule an activity having 5 activity as a predecessor one of in all ready in progress and one is Constraints which is fouandation ready for Instal...
predecessor Constraints activity starting
date is 29 Jun 09* ( Activity DC00100)
successor of above actvity is Installation of equipment.
(activity EQ001010)
which will be start on 29 jun-09
I have links ss with Activity DC00100 with 0 lag as (predec)after schedule f9
i am wondering activity EQ001010 start date is 20 april 09
can any one advise why it is so...
Thanks
shahzad
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?