activity date not changing

Shahzad AhmadMember for 18 years 8 months
Created
3
2
0
Hi all

In P6 schedule an activity having 5 activity as a predecessor one of in all ready in progress and one is Constraints which is fouandation ready for Instal...

predecessor Constraints activity starting
date is 29 Jun 09* ( Activity DC00100)

successor of above actvity is Installation of equipment.
(activity EQ001010)

which will be start on 29 jun-09

I have links ss with Activity DC00100 with 0 lag as (predec)after schedule f9

i am wondering activity EQ001010 start date is 20 april 09

can any one advise why it is so...

Thanks
shahzad


3 replies

Oldest first
  1. 0
    Ali Farhat ·
    I am not sure I followed you, please clarify more.
  2. 0
    Patricia Le Clainche ·
    Hello,

    Some information are missing before giving you a answer :
    - Which kind of relationship do you have for the other 4 predecessors ?
    - Is it logical to get 5 predecessors if one is SS ? Maybe links are not correct ?

    Best regards.
    Patricia


  3. 0
    Kashif Khan ·

    i am not clear on ur

    i am not clear on ur statement but .....you should check if the activity has constraints ,otherwise if you want your desired date then play with lags + or -.

Log in or join to reply