Is P6 Sometimes Ignoring Actuals?

Anoon IimosMember for 20 years
Created
1
2
0
Dear All,

I’m not really sure about this but it happened when I’m running a schedule with a certain activity that has an actual start earlier than the Data Date. The bar still goes with the Data Date and hasn’t started on the Actual Date, though the status shows an actual duration and a remaining duration.

Note: there is no % progress, only actual start; scheduled by retained logic

any idea?

1 reply

Oldest first
  1. 0
    Anoon Iimos ·
    I’m sorry, i’ve seen a very thin line in the actual start and I dragged it and it showed blue bar (which means progress), but I don’t want to see progress, Is it possible?