Autocalculate actuals units with Phisical % comp.

Mirko PirasMember for 18 years 7 months
Created
9
5
0
Goodafternoon at everybody!
Only one simply question...for you simply but not for me!
Is possible to autocalculate the actual units based on my phisical (then manual insert) % complete of activity an its budgeted units?
For example, if my phisical % complete of activity is 50% ad my budget units are 10.000 the actual units are 5.000.
I have tried all with only one autocompute system....about the schedule % complete of activity...
Are there any options...??!!
Thank you at everyone and sorry for my "basic" english!!
I Have Primavera P6

Mirko.

9 replies

Oldest first
  1. 0
    Alex Wong ·
    Hi Mirko

    One of the options is to use - > Project Option - Calculation
    "Update Actual Unit when duration % complete changes"

    This will automatical change the actual unit when you changes your "Duration % Complete" - But not the Phical % Complete.

    Before you run this option you can run a global change to align the duration % Complete with Physical % Complete.

    But because you updated the duration % Complete it will affect some of the activity type on the remaining duration

    Need to test run it before you can use this process.

    HTH

    Alex
  2. 0
    Paul Harris ·
    The Units % Complete will update your Actuals Units and a change to actual units will update the Units % Complete.

    If you make the activities’ % Complete type equal to Units then this will link the Units% Complete to Activity % Complete and this value will be displayed on the bars.

    The Physical % Complete field may be linked to the Activity % Field by setting the activities % Complete type equal to Physical.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au
  3. 0
    Yusuke Kamui ·
    Hi Paul,
    How can you do it?....
    "The Physical % Complete field may be linked to the Activity % Field by setting the activities % Complete type equal to Physical."

    Where to set it?
  4. 0
    Mirko Piras ·
    Hi Paul, thanks for idea...but how can you do it?....
    "The Physical % Complete field may be linked to the Activity % Field by setting the activities % Complete type equal to Physical."

    Have a nice day.

    Mirko.
  5. 0
    Paul Harris ·
    In the Activities Workspace, Activities details, General tab.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au
  6. 0
    Yusuke Kamui ·
    Hi Paul,
    What I’m expecting is to see the "physical % complete" to be calculated up to the project summary. Right now, if I enter 5% physical complete on a task, the overall project physical % complete is still showing 0% even though I have some tasks underneath having physical % complete. How come??? How to have the overall project’s physical complete status?
  7. 0
    Paul Harris ·
    You can not roll up Physical % complete as they may all be calculated on a different basis.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au
  8. 0
    Alex Wong ·
    You need to run summerized project in order to see the summary %

    HTH

    Alex
  9. 0
    Anoon Iimos ·
    there’s a workaround to roll-up physical % complete, consult your PAR

Log in or join to reply