Level of effort activity’s actual progress

Yasser ElyosefiMember for 21 years 6 months
Created
4
1
0
Hello Planners,

I’m using P6. I don’t use units or costs in my project (only durations).

I updated all activities manually except a level of effort activity that calculates its Activity % Complete automatically.

The current progress should show 25%, but it only shows 11%. By changing the % complete to 25% and run the schedule it returns back to 11%.

P6 rule of calculation is:
Activity % Complete = Duration % Complete = (Original Duration – Remaining Duration) / Original Duration.

But I want to set the level of effort activity to calculate as follows:
Activity % Complete = Actual duration / At Completion duration.

Is it possible? How?

Regards,

Yasser

4 replies

Oldest first
  1. 0
    Steven Oliver ·
    Change the Percent Complete Type to Physical
  2. 0
    Yasser Elyosefi ·
    Thanks. But in this case I need to manually calculate the progress every time I update the schedule

    My target is to set the level of effort activity to automatically calculate progress as follows:
    Activity % Complete = Actual duration / At Completion duration.

    Is there a way for that? How?
  3. 0
    Steven Oliver ·
    Use a Global Change

    You will need to use 2 action statements, one to do the Actual/At Completion part and then another to multiply this result by 100 to arrive at a percentage value.
  4. 0
    Yasser Elyosefi ·
    That means there is no built-in function in P6 to do it ??!!

Log in or join to reply