Level of effort activity’s actual progress
In the Open Standard
Yasser ElyosefiMember for 21 years 6 months
- Created
- 4
- 1
0
Hello Planners,
I’m using P6. I don’t use units or costs in my project (only durations).
I updated all activities manually except a level of effort activity that calculates its Activity % Complete automatically.
The current progress should show 25%, but it only shows 11%. By changing the % complete to 25% and run the schedule it returns back to 11%.
P6 rule of calculation is:
Activity % Complete = Duration % Complete = (Original Duration – Remaining Duration) / Original Duration.
But I want to set the level of effort activity to calculate as follows:
Activity % Complete = Actual duration / At Completion duration.
Is it possible? How?
Regards,
Yasser
I’m using P6. I don’t use units or costs in my project (only durations).
I updated all activities manually except a level of effort activity that calculates its Activity % Complete automatically.
The current progress should show 25%, but it only shows 11%. By changing the % complete to 25% and run the schedule it returns back to 11%.
P6 rule of calculation is:
Activity % Complete = Duration % Complete = (Original Duration – Remaining Duration) / Original Duration.
But I want to set the level of effort activity to calculate as follows:
Activity % Complete = Actual duration / At Completion duration.
Is it possible? How?
Regards,
Yasser
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?